Product change orders: from the request to the new version, step by step

Nobody edits the components of a product silently. A change request is written with its reason and details, a manufacturing manager approves it, then the system applies it as a new version of the components, keeping a record of every version, who changed it and why. The pictures show an iron works with sample data, in the Arabic interface.

Part of Product change orders
  1. 1. Request a change Open Manufacturing, then Products, then the product components, and open the components of the product you want to change. At the top is a Request a change button, beside the reference a Version field, and a Changes button with the number of change requests on it. Press Request a change.
    1. Request a change
  2. 2. Write the change The change request shows the product components, the product and the current version, then the reason, such as a cheaper supplier, a quality problem or a new design. The Components tab has one line per change: Add a new component with its quantity, Remove a component, or Change quantity from the current quantity to the new one. The Work steps tab, when work steps are on: add a step, remove it or change its time. The Effective date is optional: the change applies from that day, or right after approval when it is empty.
    2. Write the change
  3. 3. Send and approve Press Send for approval and the state becomes To approve, and the manufacturing managers get an activity to review it. The manager presses Approve or Refuse. Back to draft returns the request for editing. Once sent, the request cannot be edited, and the state moves only with the buttons.
    3. Send and approve
  4. 4. Approval through the Approvals app The Product change path in the Approvals app ships switched off, so a manufacturing manager approves directly. To send requests through an approval path, switch the Product change path on in the Approvals settings. Then the request goes to Approvals, and the manager cannot approve it directly until the path ends.
  5. 5. Apply the new version After approval, a manufacturing manager presses Apply from the effective date. The system makes a new version of the product components with the next version number and the changes, archives the old version, and links both to the request. A New version button shows on the request, with a note of what was added, removed and changed.
  6. 6. Open manufacturing orders After applying, an Open manufacturing orders tab shows the draft and confirmed orders that were on the old version. For each one the manager chooses Update to move it to the new version, or Leave as is. An order already in production keeps the version it started with.
  7. 7. The change history Open Manufacturing, then Products, then Product changes: one row per request with its number, the product, the version, the new version, who asked, the effective date and the state.
    7. The change history