Why did the cost change? Cost variances after delivery, step by step
When the manufacturing of a priced request ends, the system puts its actual cost next to the expected cost of the cost sheet, then splits the difference into five reasons, in figures. It needs the Design and engineering app and the real production cost. The pictures show an iron works with sample data, in the Arabic interface.
-
1. The After delivery tab Open Design and engineering, then Pricing requests, and open a request whose manufacturing has ended. The After delivery tab shows once its manufacturing order is done: the expected cost, the cost after purchase, the actual cost split into actual materials, actual work and actual other costs, the estimate accuracy (%) and the delivery date.
-
2. Why did the cost change? Under the figures is the Why did the cost change? table with five rows: material price difference when a material costs more or less per unit than on the cost sheet, material quantity difference when more or less was used than planned or materials not on the sheet, hour rate difference when the hour of a line cost more or less, hours difference when the work took more or fewer hours, and other costs for other costs and rounding. At the bottom, the total difference: actual cost minus expected cost. Over in red, under in green, with a sentence beside each row that explains it.
-
3. Detail per material and line or machine Open Detail per material and work centre under the table: one row per material and per line or machine, with the variance type, the expected and actual quantity, the expected and actual price, and the difference in your currency. You see which material raised the cost and which line took longer than planned.
-
4. Recompute If the manufacturing order changed after it ended, for example a material issued late, press Recompute at the top of the table. The system reads the finished manufacturing orders again and redoes the actual cost and the differences. The button is for the design team only.
-
5. The Cost variances report Open Reports, then Cost variances: a pivot table that adds up the differences of every delivered request by variance type, so you see where the money goes across all orders. The search has Over the expected, Under the expected and Delivered on, and groups by variance type, pricing request, product type or designer. The list button shows the same rows as a list.