What to make this month for the most profit, step by step
The monthly production plan is part of the Manufacturing app, needs Sales, and shows when it is switched on in your workspace. It answers one question: when the resources cannot cover everything, which quantity of each product gives the most profit? The calculation runs on an optimisation engine on the server: if a message says it is not installed, contact support.
-
1. Create the plan of the month Open Manufacturing, then Planning, then Monthly production plan and press New. Pick the Month. Working days come from the company working schedule and you can change them; each work center gets its hours a day times these days. Extra shift hours per day is used in the suggestion and starts at 4.
-
2. Pick the price and cost basis Sale price from: Sales price on the product, or Average sold price (12 months). Cost from: Product cost or Bill of materials cost.
-
3. Load the data and check it Press Load data. What to make has one line per manufactured product with a bill of materials: Confirmed, Expected and Unit profit; you can change the expected quantity, the sale price, the unit cost and the Extra allowed (%) above the expected demand for stock. Resources holds the hours of each work center and the quantity of each material, which you can change.
-
4. Calculate the plan and read the result Press Calculate the plan. At the top: the expected profit, the confirmed orders covered, the Limiting resource with the Value of one more hour, and the suggestion: an extra shift on that resource, how much profit it adds and what it allows you to make. For each product: the planned quantity and its status, Extra, All expected, Part of expected, Confirmed only or Short of confirmed. The plan never goes below the confirmed orders when the resources allow them.
-
5. Try What if? Press What if? and the plan goes back to draft. Change the hours of a work center or the quantity of a material under Resources, then Calculate the plan again and compare the expected profit.
-
6. Approve and create the manufacturing orders Tick Confirm the manufacturing orders if they should be confirmed once created, so missing components are requested through their normal routes. Then Approve and create manufacturing orders. A Manufacturing orders button shows on the plan, and an approved plan does not change: make a new plan for any change.