How do I spread manufacturing orders over my lines so none misses its deadline?
Work the schedule out from the deadlines, the hours of each line and the maintenance together. In Intagya ERP you create a line schedule for a number of working days. The system spreads the open work orders over the work centers, shows a board per center, compares it with the current order sequence and lists the orders that will be late, each with a suggestion. Approving it writes the planned start and end on the orders.
A plant has three work centers and fourteen open orders. Every Sunday morning the supervisor writes the week on a whiteboard. On Tuesday a machine stops for a planned service everyone forgot, and everything shifts. On Thursday a customer calls about his order, and the supervisor learns for the first time that it will be two days late.
The whiteboard is not the problem. The problem is that the sequence lives in one person's head, and nobody else sees what a change does to it.
Why are orders late when there is enough capacity?
Because total capacity is one thing and the order of the work is another. The week may have enough hours for every order, and one is still late because it waited behind an order due much later, or because its second step sits on a busy work center. Each order has steps in sequence: finishing cannot start before assembly ends.
Line load answers one question: are there enough hours? Scheduling answers the next one: in what order, on which line, on which day?
Read: how do I know my lines can take a new order before I promise a date?
What does the system need to build the schedule?
Most of it is already there when your manufacturing orders have work orders. Open Manufacturing, then Planning, then Line scheduling, and create a schedule:
- The first day, the number of working days up to 60, the weekly day off and when the shift starts.
- Load work centers adds every center with open work orders, and its alternative centers, with the shift hours a day and the cost per hour.
- Blocked periods: maintenance or any stop of a work center from one date to another.
- From the orders themselves: the deadline, the duration of each work order and the order of the steps.
Which goal should I pick?
There are three. Best for deadlines puts delivery on time first. Fewest product changes groups similar orders so the line changes over less. Lowest cost keeps the cost of line hours down.
Start with the first. Changeovers and cost matter, but a customer waiting matters more. Try the other two once you trust the numbers.
What do I see after Compute schedule?
Four cards compare the proposed schedule with the current order sequence: orders delivered on time, line use, late orders and product changes. Then the Proposed schedule: a lane per work center with its daily capacity, and the work orders on their days.
Under the board, Orders that need your attention lists every order that will be late or is on the edge, with its deadline, expected finish and a short suggestion. For example: a number of extra hours on a given work center up to a given day is enough to deliver on time. Or, when the steps alone take longer than the time left, agree a new date with the customer.
Does anything change in the plant before I approve?
No. The schedule is a proposal until you press Approve schedule. Then the planned start and end of every work order and manufacturing order are written. If a work order was started, added or moved after the calculation, the system asks you to compute again before approving, so you never approve a stale schedule.
Enter the coming maintenance under Blocked periods before you compute. A schedule that does not know the machine stops on Tuesday will promise a date it cannot keep.
How is it different from Order sequencing?
The Order sequencing tool in the Decisions tab of the Overview page orders the week on each machine so similar orders follow each other and less time goes to changeovers. Line scheduling plans all work centers together for the span you choose, with steps that wait for each other, alternative centers, maintenance and the hours of each shift.
Tomorrow morning, create a schedule for one week, press Load work centers, check the hours of each center, enter the maintenance and compute. Read Orders that need your attention before the production meeting, not after it.
Read the line scheduling guide step by step
FAQ
How long does the calculation take?
You set the Search time between 5 and 120 seconds. If it ends before the system proves the schedule is the best, it says so and shows the best schedule it found.
Does it use an alternative work center when the main one is busy?
Yes, when the work center has alternative centers in its data. Load work centers adds them to the schedule.
What if some work orders end after the last day of the schedule?
The system shows how many under the board. Add working days or shift hours and compute again.
What do I need to use it?
The Manufacturing app, and manufacturing orders with work orders on work centers with known durations. The calculation runs on an engine on the server; if a message says it is not installed, contact support.