How do I know my factory lines can take a new order before I promise a date?
Open Manufacturing, then Order tracking, then the Line load tab in Intagya ERP. For each line or machine, in each of the next six weeks, you see the hours confirmed manufacturing orders need against the hours its working schedule gives. Under 85% green, 85 to 100% amber, over 100% red, and overloaded weeks show at the top of the page.
A customer calls the sales manager of an iron works: he wants two hundred doors before the end of the month. The manager looks at the calendar and says yes, two weeks and they are ready.
The next day the order reaches the production manager. The cutting machine is booked for an earlier order until the middle of next month. The apologies start, or the overtime does.
Nobody lied. The sales manager simply could not see what the production manager sees.
Why do we promise customers dates our lines cannot keep?
Because the number of orders says nothing about the load. Five small orders may not fill a day, and one big order can fill two weeks on a single machine.
The real question has two numbers: how many hours of work wait for this line this week, and how many hours the line actually runs. As long as both live in the production manager's notebook, every promise is a guess.
Where do I see the load of each line and machine in the coming weeks?
Open Manufacturing, then Order tracking, and press the Line load tab beside the Orders tab. One row per line or machine inside the factory, one column for each of the next six weeks, the week running from Saturday to Friday. The first column is This week.
Each cell shows the load in percent, a bar and the hours, such as 12 of 40 hours. Under 85% green, 85 to 100% amber, over 100% red. Press a cell to open the work steps in it.
How does the system count the hours needed and the hours available?
The hours needed are what is left in the open work steps of confirmed manufacturing orders: expected time minus time already worked. An order half done loads the line with its remaining half only.
The hours available come from the working schedule of the line or machine, minus the time off and public holidays in that schedule. So a holiday week is tighter than the others without you counting it by hand.
Some things are left out on purpose: lines run by a subcontractor, draft manufacturing orders, and work planned after the six weeks. A draft is not a commitment yet, so it books no hours.
What do I do when a week turns red?
An Overloaded weeks warning shows at the top of the page: one line per line and week with the load and the extra hours, worst first. The Open these work orders button opens every work step in those weeks.
From there you have three ways out: move some steps to another line that does the same work, move them to a lighter week, or decide on an extra shift knowing exactly how many hours you need. Red is not a disaster. It is a warning that arrived before the customer did.
Have the sales manager open Line load before any promised date. One look at the line the order will run on saves the apology call a week later.
Why does a line show no load?
Because it has no working schedule. Then a note under its name says its load cannot be measured, and a manufacturing manager sees a Choose a schedule button. Pick its schedule and the percentage appears.
When there are no open work steps, a No open work orders note shows and every line is free.
Tomorrow, start by checking the working schedules: each line and machine with its right schedule, shifts and holidays. Then open Line load in the weekly production meeting instead of asking about each order by name.
Read the line load guide step by step
FAQ
Do draft manufacturing orders count in the load?
No. Only what is left in the work steps of confirmed manufacturing orders counts.
How many weeks ahead do I see?
Six weeks, starting with the current one, each running from Saturday to Friday.
Are holidays taken off the hours available?
Yes. Time off and public holidays in the working schedule of the line or machine are taken off.
What happens to a step that is late on its week?
It counts in the current week, and the cell shows how many with the word late.